Skip to content Skip to footer

STACK completes first phase of Toronto campus

Image: STACK Infrastructure

STACK Infrastructure has delivered the first phase of its flagship Toronto campus.

The first facility on the campus will provide 8 MW capacity with a further 48 MW of planned expansion, for a total of 56 MW.

Toronto-based property developer First Gulf partnered with STACK to deliver the initial facility by renovating an existing building. STACK has said the next 24 MW phase of development is scheduled to open in the second quarter of 2026, and will be powered by Toronto Hydro using 100% renewable energy sources.

The new campus is located close to 151 Front Street in Toronto, Canada’s largest carrier hotel and primary internet exchange point in the city.

“In a market that continues to see a high absorption rate for data center capacity, STACK is proud to deliver the first phase of our Toronto campus,” said Brian Cox, Chief Executive Officer of STACK Americas.

“We look forward to deploying the next phase of this flagship campus to address our clients’ needs while vitalizing the local economy.”

You may also like

Stay In The Know

Get the Data Centre Review Newsletter direct to your inbox.