When a connection slips, a developer can still be paying to build and finance a site that cannot take its planned load. Clarence Philipneri, CFO at Salute, explains what finance teams can do before they commit capital.
Power has always been a constraint in the data centre industry, but over the last three to five years, it has begun to dominate boardroom discussions. It used to be a question for operational teams to consider, but more recently it has become a serious financial risk which sits within the CFO’s remit.
Large developments with committed capital and uncertain grid connection dates have driven the change at boardroom level. The industry used to plan its builds with little thought for grid connection, confident the power would be there when a project came online, but in more recent years that confidence has dissipated, as the demand from AI infrastructure continues to grow far faster than the power grid can keep pace with.
When a site is left waiting for connection
Operating across 100+ markets, alongside many of the largest operators, gives us clear visibility into where the strain is landing. It has not only been confined to one country. We are seeing similar patterns repeating globally, with grid connection queues that used to be measured in months now stretching into years across the majority of major markets.
There are several factors that drive the real damage to pricing certainty. Capital deployed into the project sits idle while the build is still waiting to become operational. Another is the length of the delay itself, which can range anywhere from months to years and rarely matches the expected timelines put into place at the beginning of the project. And when a site finally goes live but runs below the levels the business case was built on, the result is a net negative for operators and investors.
Then there is the regulatory side of the picture. Queue position and approval timelines follow no predictable schedule, and that unpredictability has a cost of its own. For builds that cannot connect, the consequences compound. For example, capital already invested earns nothing, affecting the return on investment. From there, customer commitments also fall under pressure, and penalty clauses are triggered as costs continue to climb.
Pushing a connection back by even a matter of months changes the rate of return significantly, particularly where the pricing was built around speed to market. And in the most constrained locations, we are seeing facilities switched on at only a fraction of what they were designed for, unable to reach their full intended capacity.
The gap between what was forecast and what the asset actually delivers makes every number that follows harder to defend, and investors and board members will scrutinise why things have moved. This is where the problem lands directly with the CFOs.
Capital in place, connection pending
In the first quarter of 2026, local opposition blocked or delayed at least 75 data centre projects worth around $130 billion, the most in any single quarter on record, according to NBC News. But what that number obscures is where the money already sits. These are not projects that are still hunting for funding. The land has been bought, the capital committed and construction well underway. But then the site stalls, held up not by any shortage of demand, but because the right decisions had not been taken beforehand. It follows a consistent pattern, where land is secured, construction completed, capital deployed, and yet the facility cannot be brought fully online as it’s missing one input the developer won't be able to provide themselves: a grid connection.
On-site generation can bridge the gap, but it rarely pays at scale. The costs of a half-powered facility are easy to underestimate because each looks survivable in isolation: capital sitting idle and revenue pushed out a few quarters, while customers with their own deadlines start looking elsewhere. Any one of those can be absorbed. But together, they erode a real share of the return the project was intended to deliver.
How finance leaders should respond
Power needs to be built into the investment case from day one, which means real identification of grid access, connection timing and the regulatory position before capital is secured and a location is fixed.
Delays do not need to be scheduled, but they do need to be in the forecast. You cannot promise investors a timeline you cannot fully trust. That also means building models flexible enough to handle phased energisation, and being open to alternative power strategies where the grid cannot deliver.
The key is to bring finance, development and operations together at the very start of the build process. When those teams are aligned from day one, decisions about whether a project should proceed, and where, are made with far greater accuracy. The operators who get this right, and who can secure power reliably and at scale, will hold a clear advantage over those who cannot. And with that comes something increasingly valuable in this market, investor confidence built on trust.